May 2026 Update

The LinkUS initiative is delivering on its promise to transform mobility in Central Ohio. These progress reports highlight key achievements, project timelines and upcoming opportunities for community engagement.

View Full May 2026 Progress Report
May 2026 LinkUS Progress Report Cover

Recent Achievements

  • Extended COTA Service: Late-night service began May 5, with routes now running past midnight on downtown lines and crosstown lines.
  • Community Engagement: Over 3,700 residents engaged across multiple community events.
  • Transit-Supportive Infrastructure: 83 projects approved to create 150 miles of sidewalks, bikeways and trails.
  • BRT Development: All three projects are advancing in the design phase, with federal funding milestones reached.

Project Status Updates

Each Bus Rapid Transit line is making steady progress toward implementation:

  • West Broad BRT: Final design near completion with construction beginning early 2026.
  • East Main BRT: Advancing toward completing the 60% of design milestone by summer 2025.
  • Northwest BRT: Granted entry into Project Development by the FTA under the Capital Investment Grant Small Starts program.

Get Involved

COTA modifies service three times per year on the first Monday of January, May and September. To ensure all those within our communities have an opportunity to understand COTA’s decisions and provide input, COTA conducts several meetings throughout the year and encourages the public to attend. Learn more at COTA.com/servicechanges.

LinkUS progress reports are published three times annually to coincide with COTA service changes in January, May and September.